Hall WTW - Anglian Water Special Projects Amp 5

This was a new water treatment facility on a greenfield site, with a value of £46M. It comprised a raw water pumping station from the river trent, 5km of raw water pipeline, a raw water storage reservoir and a water treatment facility with final pumping station. It also included works to tie in to the existing water treatment works, already running and providing water to the City of Lincoln.

I was sole planner on this contract and my responsibilities were as follows...

  • Prepare the tender programme for the Amp 5 clean water projects.

  • Helped prepare Civil & M&E design programme.

  • Prepare and maintain the design, construction and commissioning schedule for the project, across all disciplines.

  • Implement resource / cost loaded programmes to facilitate Earned Value Analysis

  • Update the schedules fortnightly and produce client and project manager reports

  • Communicate with the project teams, regarding progress, scheduling and resourcing.

  • Prepare Monthly Board and Client reports, forecasting progress and out turn costs by employing Earned Value techniques.

  • Prepare Earned Value analysis reports.

  • Liaise with various subcontract companies, regarding monitoring of progress and resourcing levels.

  • Acquire and interrogate subcontractors schedule programs, incorporating the data into the construction program and confirming feasibility or highlighting potential problems.

  • Prepare Tender Programmes for potential future projects, on behalf of Galliford Try.