This was an extension to an existing water treatment works in Northern Lincolnshire, with a value of around £25M. I was sole planner on this job, in a part time capacity alongside the Hall WTW project detailed elsewhere on this website.

In order to increase the output of the non-potable plant and improve performance of the existing treatment facilities, the following was required:
• Construction of a zebra mussel trap, to serve both works and new microstraining facilities for the non-potable works.
• Provision of new clarifiers and rapid gravity filters, for the non-potable works, plus associated chemical dosing facilities.

• Improvements to the wastewater handling, treatment and waste disposal facilities serving both works

• Construction of new blind lagoons, to receive overflows and process waste from both works.
 

Elsham WTW - Anglian Water Special Projects Amp 5